Operating a Quarry

Project Details

Client Name: RMC Ready Mix India Ltd
Location: Sonnappanahalli village, Bangalore, Karnataka

Objective/Challenge

  • To operate a quarry next to village.
  • To feed a 300 Tons Per Hour crusher from Quarry not even producing a days requirement.

Approach

  • When Uttam took up the quarrying contract for RMC, the first thing that was done was to develop the proper benches in the Mine and use controlled blasting.
  • Each blast was monitored for vibrations and noise produced to ensure that vibrations and noise generated in the blasting is within the prescribed limits.
  • To feed a 300 Tons Per Hour crusher from Quarry not even producing a days requirement.

End Result

    • Machinery Deployed
    • Here is the result in fortnight wise production (on single shift basis)
Fortnight Output In Tonn
1 1471.98
2 3711.93
3 6431.49
4 2864.90
5 8252.03
6 6145.05
7 5074.44
8 3742.77
9 8236.24
10 7601.81
11 7121.00
12 4334.28
13 2022.93
Total 67010.83